Heidelberg Materials – Crushing Plant & Workshop

Structural steel and mechanical installation works for the Heidelberg Materials Crushing & Screening Plant and Transport Workshop. 

Client

Heidelberg Materials Australia

Project Type & Industry

Precast Aggregate

Delivery Method

Subcontract

Principal Contractor

Heidelberg Materials Australia

Location

Luscombe, Queensland

Delivery Period

2026 - 2026

Status

Complete

Project Scale

Live quarry infrastructure project including processing plant structures, conveyor systems, access platforms, and workshop construction.

Services Delivered

Structural Steel Erection & Mechanical Installation

Project Highlights

Live Quarry Environment

Works completed alongside active operations

Integrated Scope

Structural, mechanical, and workshop construction works

Industrial Processing Infrastructure

Crushing and screening plant installation

2025–2026

Multi-stage delivery program

Project Overview

The Heidelberg Materials Crushing Plant & Workshop project in Luscombe, Queensland forms part of ongoing infrastructure upgrades supporting quarry processing and transport operations.

JKR Group Australia Pty Ltd was engaged by Ridge Projects Australia Pty Ltd to deliver the structural steel and mechanical installation works for the new crushing and screening plant, associated conveyor infrastructure and transport workshop facility.

JKR’s scope included fabrication coordination, delivery, erection of structural steel, installation of access platforms and conveyor support systems, along with construction of the transport workshop. All works were completed within a live quarry environment, requiring detailed planning, strict safety controls and close coordination with ongoing site operations.

Project Challenges

  • Live Operational Environment: The facility incorporated a complex steel structure exceeding 21 metres in height, requiring staged erection and accurate sequencing across multiple levels. 
  • Structural & Mechanical Coordination: The integration of structural steel, conveyor systems and processing infrastructure required accurate sequencing and installation alignment. 
  • Safety & Quality Compliance: All works were delivered in accordance with strict project-specific safety and quality requirements within a high-risk industrial environment.

Solution

JKR Group implemented a staged construction approach to safely coordinate structural and mechanical works alongside ongoing quarry operations.

The team managed fabrication coordination, steel erection and installation activities in line with project sequencing requirements, ensuring all structures and systems were installed efficiently and to specification. Close collaboration with the head contractor supported safe site access, workflow continuity and program delivery throughout the project.

 

Services Delivered

Structural Steel Erection

Crushing Plant and Transport Workshop structures, including the installation of structural steel and 10,500m² of roof and wall cladding

Crane Hire & Lifting Services

JKR supplied and operated its own crane fleet for all lifting, erection, and installation activities, ensuring efficient project delivery

Mechanical Installation

Installation of conveyor support structures and associated mechanical components throughout the crushing plant.

Access Systems Installation

Supply and installation coordination of access platforms, walkways, and stair systems.

Project Coordination & Logistics

Fabrication coordination, delivery management, and sequencing of materials to support the construction program.

Outcome

The project will deliver upgraded quarry processing infrastructure and transport facilities to support ongoing operational efficiency at Hanson’s Wolffdene Quarry.