— Design and construction of a purpose-built early childhood education facility, including civil works, structural construction, building works, outdoor play areas, and services integration.
Client
YWCA Canberra
Project Type & Industry
Education / Community Infrastructure
Delivery Method
Design & Construct
Principal Contractor
JKR Group Australia Pty Ltd
Location
Murrumbateman, NSW
Delivery Period
2017
Status
Complete
Project Scale
8,000m² community and education development.

Services Delivered
Design & Construct, Civil Works, Structural Steel Supply & Erection, Building Construction, Services Coordination
Project Highlights
8,000m² Development
Purpose-built early childhood education facility.
Design & Construct
End-to-end project delivery solution.
115-Place Childcare Centre
Supporting growing community demand.
Education Infrastructure
Modern learning environment for children, educators, and families.
Murrumbateman, NSW
Delivered within a growing regional community.
— Project Overview
JKR Group was engaged under a full design and construct contract to deliver the YWCA Canberra – Fairley Early Childhood Service in Murrumbateman, NSW. The project involved the development of a purpose-built early learning facility designed to provide a modern, safe, and engaging environment for children, educators, and families.
Located within the growing Murrumbateman community, the facility was developed to support increasing demand for quality early childhood education services and provide a welcoming community hub for local families. The completed centre accommodates up to 115 children and features purpose-built learning environments designed to support early childhood development and education.
JKR Group provided a fully integrated construction solution, managing all aspects of design development, civil works, building construction, services coordination, and project delivery through to completion.

— Services Delivered
Design & Construct Delivery
Complete project management from concept design through to construction and final handover.
Civil Works
Delivery of site preparation, earthworks, drainage, hardstands, and supporting infrastructure works.
Structural Steel Supply & Erection
Supply and installation of structural steel components supporting the facility's construction
Building Construction
Construction of a purpose-built childcare and early learning facility tailored to community and educational needs.
Services Coordination
Management and integration of electrical, hydraulic, mechanical, and associated building services throughout the development.